In short
The BTnet leased line installation process runs from enquiry to Service Start Date: needs and availability check, quote and order, site survey, any excess construction or wayleave work, a Customer Committed Date from BT, engineering works, equipment fitted and tested by BT, then your acceptance tests. BT says installation can take up to 70 working days, depending on survey.
Want help with BTnet?
We can plan it with you or do it for you. Tell us where you are up to.
The installation process at a glance
BTnet is a dedicated access line from your premises into BT's network. Because the line is built for your site, every order goes through a survey and an engineering stage before the service starts. In plain words, these are the steps under BT's terms and help pages:
- Enquiry and needs. You tell us the address, what the connection is for, the speed you need now and later, and whether the site must stay online through a fault.
- Availability and desktop survey. BT gives an up-front lead-time prediction based on average installation times in your area and a desktop survey that places the job in a delivery "category".
- Quote and order. We prepare a written quote for the plan, speed, contract term and any resilience. When you order, BT's credit vetting may apply.
- Site survey. The survey is the first step of any order. It confirms a suitable access line can reach your site and gives a firm expectation of lead time.
- Extra engineering and permissions. If the survey finds work beyond the normal level, excess construction charges may apply. If the route crosses land or a building you do not own, a wayleave agreement may be needed.
- Customer Committed Date. After the survey BT gives a Customer Committed Date (CCD) for delivery, or an estimated date where it cannot commit to one.
- Engineering works. The access line is built and run into your building, ready for the network terminating equipment (NTE).
- Equipment fitted and configured. The NTE is installed and, unless you chose BTnet wires only, BT's managed router or Meraki equipment is fitted and configured.
- BT's tests. BT configures the service and runs standard tests, pinging the managed equipment or, on wires only, the port.
- Your acceptance tests. You have five Business Days to carry out acceptance tests. If you do not tell BT otherwise in that time, the service is treated as accepted.
- Service Start Date. Billing starts, and BT's availability service level applies, from the Service Start Date.
Each stage has its own page in this section, and the questions most people ask are answered below. If you want the short version for your site, contact us with the address and we will tell you what the early steps look like there.
Before you order: availability, design and quote
The work you do before ordering shapes everything after it. A clear brief avoids changes later, and changes after the order can move dates.
- Check availability properly. There is no instant answer for a leased line. BT's prediction comes from local averages and a desktop survey, and only the site survey gives a firm answer. See how BTnet availability is checked.
- Choose the plan. BTnet wires only, a managed Cisco router or Meraki with BTnet Security. The plan decides what equipment BT fits and where BT's responsibility ends.
- Size the bearer and speed. The bearer is the physical access circuit; the port speed is the bandwidth you buy on it. Choosing a bearer with room to grow means later speed changes can be made with Bandwidth Flex instead of a new installation. See bearers and port speeds.
- Decide on resilience now. A second access line is far easier to plan at the start, when route separation can be looked at in the same survey.
- Agree an ECC limit. BT's terms let you set a limit for excess construction charges in the order. Within it, BT carries on; above it, BT re-quotes. We explain the choice when we quote.
- Expect credit checks. BT's terms say you may be credit vetted and BT may ask for a deposit or other security for payment.
Our questions to ask before you order turn this into a checklist, and BT leased line cost explains how each choice affects the price.
After you order: survey, permissions and your committed date
Once the order is in, BT arranges the surveys needed to confirm that a suitable access line can reach the site. The site survey is where the plan meets the building: the route in from the street, the entry point, the path to your comms room and where the equipment will go.
Three things can follow from the survey:
| Survey finding | What happens next under BT's terms |
|---|---|
| Normal installation | BT confirms the job and gives a Customer Committed Date |
| Extra engineering within your agreed ECC limit | BT carries on and completes the additional works as part of delivery |
| Extra engineering above your limit, or no limit set | BT may send a new quote; you accept it and work continues, or the order for that site is cancelled |
| Work on land or in a building you do not own | A wayleave or landlord consent is arranged before that work can start |
The Customer Committed Date is the date delivery is due to start. BT uses commercially reasonable endeavours to meet it, and if BT misses it, BT's on-time delivery service level lets you claim a credit against the service introduction charges. Where BT cannot give a committed date, it gives an estimated date instead. If you ask for a change to the order, BT may revise the CCD to fit. Our guide to BTnet lead times covers dates in detail.
Not sure which plan applies to you? Ask us
Tell us about your organisation and we will point you to the right plan.
Installation day: what happens on site
Engineering visits happen in Business Hours, which BT's terms define as 08:00 to 17:00 on a Business Day, unless agreed otherwise. You need someone on site who can let the engineers in and escort them where required.
On the day, the usual sequence is:
- The access line is brought in along the route agreed at survey, using the trunking, conduits or cable trays you have prepared.
- The NTE is fitted. This is BT's termination point for the line. On wires only, BT's responsibility ends here.
- Managed equipment is installed. On the Cisco router or Meraki options, BT fits and configures its equipment, and the boundary moves to the equipment's LAN port.
- Internal cabling is connected. Cabling between BT's equipment and your own network is your responsibility under BT's terms, so have it ready or arranged.
- BT tests the service. BT runs its standard tests and confirms when the service is ready for your acceptance tests.
Your site preparation checklist covers space, power, cabling and access in detail. A missing piece of preparation on the day, such as no access to a riser or no power where the equipment is going, can stop the visit going ahead.
Acceptance tests and the Service Start Date
When BT has configured and tested the service, it either confirms the Service Start Date or tells you the service is ready for your acceptance tests. Under BT's terms:
- You carry out acceptance tests within five Business Days of BT's notice.
- You can confirm acceptance in writing, or the service is treated as accepted if you give no notice to the contrary within that period.
- If a test fails and you tell BT within the period, BT remedies the problem and then confirms the Service Start Date.
- BT does not test wireless access, so test any BTnet Wi-Fi yourself.
- BT may invoice from the Service Start Date even if other services that depend on BTnet, such as a new phone system, are not ready yet.
That last point is worth planning for. If BTnet is the foundation for a phone move or a cloud migration, line up those projects so they can follow soon after the Service Start Date. Simple checks for acceptance: a wired test of speed in both directions (our leased line speed test guide explains how), your static IP addresses working, and your key applications reachable.
Prefer a hand with this?
We can help you plan it and set it up, alongside your own team.
What can slow an installation down
| Cause | Why it matters | What helps |
|---|---|---|
| Excess construction | New duct or civil works take time and may need a re-quote | Survey early and agree an ECC limit you are comfortable with |
| Wayleaves | Work on land or in a building you do not own waits for the owner's signature | Give landlord or managing agent details at order and ask them to expect the paperwork |
| Site access | BT's terms let BT charge as if installed from the scheduled date if you delay access unreasonably, including no access within five Business Days of BT asking | Name a site contact who can escort engineers in Business Hours |
| Site not ready | No space, power or cable route for the equipment | Work through the site preparation checklist before installation |
| Changes after order | A change of speed, plan or location can revise the CCD | Settle the design before ordering |
| Incomplete information | BT may review charges if site information is wrong or changes | Give accurate health, safety, security and access details up front |
BT's terms also say BT is not liable for delay where another supplier delays the supply BT relies on, or where legal or regulatory restrictions prevent it. In practice, the biggest single factor you control is how early you start.
How Forever Communications helps
Forever Communications is an Authorised Supplier for BT. We cannot set BT's dates, but we can make sure your order is clear, complete and well prepared, which is what keeps installations moving:
- Before you order, we help you choose the plan, bearer, speed and resilience, and explain what the desktop survey category means for your site.
- At quote stage, we set out the ECC limit, credit vetting and contract points so there are no surprises later.
- During delivery, we can help you prepare the site, line up landlord consent and understand each update on your committed date.
- At go-live, we can help you plan acceptance tests and the move of your phones and systems onto the new line.
Planning a move or a new site? Start the conversation early. Contact us for a BTnet leased line quote.
Installation, surveys and permissions
Why buy BTnet from Forever Communications
Forever Communications is part of Forever Group and an Authorised Supplier for BT. We supply BTnet, BT's dedicated leased line internet service, to businesses, schools, charities and public sector organisations, and we help with each step from first enquiry to go-live.
- The right BTnet option for you: we help you choose a speed, bearer, router and resilience option that fits how your sites actually work, from BTnet plans to BTnet speeds
- A clear quote: BTnet is priced per site, so we check availability at your address and set out what is included; see leased line cost
- Installation managed with you: we explain the survey, any wayleave or construction steps and the installation process, and keep you updated on progress
- Connected services in one conversation: phones with BT Cloud Voice, Wi-Fi, firewalls and backup lines, so the whole set-up is planned together
- Help after go-live: we can help with faults, changes and upgrades, with the support arrangements confirmed in your quote
BTnet is a business service. Service levels, lead times and features are BT's and are confirmed at order.
Frequently asked questions
How long does BTnet installation take?
BT says installation can take up to 70 working days, depending on the survey. BTnet Express typically takes 35 to 40 working days. Your firm date comes after the site survey. See BTnet lead times.
What is the first step of a BTnet installation?
The site survey is the first step of any BTnet order, according to BT. Before you order, BT can give a predicted lead time from local averages and a desktop survey.
Do I need to be on site for the installation?
Yes, or someone acting for you. BT's terms ask you to give access in Business Hours, 08:00 to 17:00 on a Business Day, unless agreed otherwise, with a contact to escort BT's engineers. Unreasonable delays in giving access can lead to charges under BT's terms.
What are acceptance tests on a leased line?
Tests you carry out after BT confirms the service is ready, to check it works as ordered. Under BT's terms you have five Business Days; if you raise no issue in that time, the service is treated as accepted.
When does billing start on BTnet?
From the Service Start Date. BT may invoice from that date even if services that depend on BTnet, such as a new phone system, are not yet ready.
Can I cancel a BTnet order during installation?